  • Updated: 4 months 3 weeks ago
    NOTICE Water Main Replacement Project Sewickley Water Authority will be replacing the water main and installing new service...

    Status Update (chronological):

    8.22.19 Update: Main line installation is complete, there are two tie-ins to existing lines that need completed at Beaver Street and Canterbury Lane that will require interruptions of service. The work will take place in the next two weeks and impacted customers will be notified. Currently all customers on Grove Street between Beaver Street and Centennial Ave are connected to the new line except for the Britney Normandy Apartments which will be completed in the next two weeks in conjunction with the Beaver Street tie-in. The contractor is currently working on swapping services on Grove Street between Centennial Avenue and Backbone Road. It is anticipated that the work will be completed by August 23rd. Going forward the anticipated schedule is: August 27 Tie-in on Canterbury Lane, cap the old line at Centennial Avenue. August 28-30 Patching on Grove Street between Centennial Avenue and Backbone Road. September 3-5 Swap service for Britney Normandy Apartments, make final tie-in at Beaver St. September 9-12 Final patching and landscape restoration. Please note that following the competition of the water line work, the Borough will be staring work on sanitary and storm sewer improvements the length of Grove Street.
  • Updated: 3 months 2 weeks ago
    NOTICE Water Main Replacement Project Sewickley Water Authority will be replacing the water main and installing new service...

    Status Update (chronological):

    8.21.19 Update: The construction of the new main is complete with all the customers being served from the new line. Paving and Landscape restoration will be completed at a future date to be coordinated with the borough contractor.